LSS 50MW MERCHANG, TERENGGANU

Project : Interconnection facility generation of 50MWac from PV solar farm to TNB grid.
Site location : Merchang, Terengganu, Malaysia
Start Date : March 2017
Completion Date : May 2019
Scope of work :
Establishment of interconnection facility from solar PV plant to TNB grid. The works include:
- Engineering design for civil works, electrical (primary and secondary equipment);
- 33kV underground cable (800m) from PV plant to medium voltage interconnection facility;
- Loop-In Loop-Out (LILO) overhead transmission line TNB to new solar substation;
- Construction of civil works for MV interconnection facility and TNB’s HV buildings, including all mechanical and electrical (M&E) equipment;
- Procurement and installation of primary and secondary medium voltage (MV) and high voltage (HV) equipment;
- Telecommunication equipment;
- Reconfiguration of TNB’s substation remote-end;
- Site Acceptance Test per TNB specification and Grid Code test (GCT)