LSS 50MW Gurun, Kedah

LSS 50MW GURUN, KEDAH

Project : Interconnection facility generation of 50MWac from PV solar farm to TNB grid.

Site location : Gurun, Kedah, Malaysia

Start Date : March 2017

Completion Date : December 2018

Scope of work :

Establishment of interconnection facility from solar PV plant to TNB grid. The works include:

  • Engineering design for civil works, electrical (primary and secondary equipment);
  • 33kV underground cable (6.2km) from PV plant to medium voltage interconnection facility;
  • 132kv underground cable (1.2km) from MV facility to TNB substation;
  • Construction of civil works for MV interconnection facility and TNB’s HV buildings, including all mechanical and electrical (M&E) equipment;
  • Procurement and installation of primary and secondary medium voltage (MV) and high voltage (HV) equipment;
  • Telecommunication equipment;
  • Reconfiguration of remote end TNB substations;
  • Site Acceptance Test per TNB specification and Grid Code test (GCT)